News

Dude. Be Nice Campaign

Massana’s Washington employees were featured in the dude. be nice campaign promoting worker safety in construction zones. dude. slow down


Massana Construction Lifts 11 Bridges in Five Counties

WED APRIL 01, 2020 - SOUTHEAST EDITION #8 - constructionequipmentguide.com

900x0_s3-47981-1s3-47981-S-GA-094_20-IR-_1000JPG-1.jpg

Punch list items are all that remain on the Georgia Department of Transportation's (GDOT) $8 million rehabilitation of 11 bridges over Interstate 20 and Interstate 16, which raised the height of bridges in Newton, Green, Morgan, Taliaferro and Laurens counties.

The contract, awarded to Massana Construction Inc., had three separate crews operating on parts of the state that were 60 miles from Atlanta and about 75 miles apart from each other between the outermost bridges.

“The focus of the project was to raise all 11 bridges to increase the clearance for trucks underneath,” explained Steve Roeser, Massana’s project manager. “It was primarily a bridge jacking job and there was a multitude of incidental work that needed to happen once the bridge was raised–the guardrail, approach decks, wing walls and other road work.”

See the whole article here…

Chattanooga Avenue bridge project completed early

Submitted by the City of Dalton • Daily citizen 12/5/2019

The Chattanooga Avenue bridge over Mill Creek was recently repaired and upgraded. The work addressed several concerns.

The Chattanooga Avenue bridge over Mill Creek was recently repaired and upgraded. The work addressed several concerns.

An extensive project to repair and upgrade the Chattanooga Avenue bridge over Mill Creek was completed in November approximately three weeks ahead of schedule. The work on the bridge took nearly two months and addressed a number of issues.

The Georgia Department of Transportation (GDOT) inspects every bridge in the state every two years, and the most recent report on the bridge over Mill Creek detailed a number of needed repairs or upgrades to address stability and safety. Dalton’s Public Works Department contracted with Massana Construction to perform the repairs with work beginning on Aug. 26 and continuing through the last week of October.

“There were several repair items on the Chattanooga Avenue bridge that required time-sensitive repair,” said Dalton Public Works Director Andrew Parker. “At some point in the past, one of the support wing walls detached from the bridge, most likely as a result of a vehicular impact. We were concerned that further failure could occur, requiring an emergency repair to make the bridge safe for travel.”

There was more work done than that. The project called for an extensive overhaul of the bridge and included repairs and upgrades both cosmetic and also structural for reasons of safety. Crews removed and replaced the existing wing walls and also the asphalt overlay on the entire bridge deck.

Crews replaced bridge deck joints, and extended the existing concrete parapets (for guardrail connection and to be raised to current standard height for safety). The project also included installation of deck pipes along bridge shoulders (to improve drainage), repair of sections of spalled concrete on deck overhang, surface preparation and painting of the steel superstructure, redress of the slope protection at each bent, installation of polymer overlay over the bridge deck, epoxy pressure injection of cracks to seal them and the addition of a guardrail for safety.

“Since this project took place in the fall, we were focused on trying to complete the project early since much of the rehab work was temperature sensitive and could not be performed in the winter months,” Parker said. “I’m proud of not only the contractor’s efforts in completion of this successful project but also our project engineer and management team that performed administration of this project from all the way from plan development through reopening of the bridge ahead of schedule.”

“We are very happy with the job that Massana Construction performed,” said project engineer Megan Elliot, one of the Public Works Department’s supervisors for the bridge repair. “The Chattanooga Avenue bridge over Mill Creek is like a brand new bridge, and should not require any real maintenance for the next 30 to 40 years.”


Georgia DOT and Massana using precast panels

Read full article here.

 

Social Media